Re: MRP configuration

$
0
0

Nassar Fathy, thanks for your answer.

 

 

Basically we need to know if during automatic purchase requisition creation (triggered by mrp), the system checks the availability stock of the plant supplier and if this stock is above the minimum stock level of the material for this plant. If this conditions does not reached, the system should not trigger the purchase requisition.

 

It is possible in the standar MRP configuration?

 

ex;

 

Plant 1000 request 20 units of material A to plant 2000.

 

The MRP should trigger the purchase requisition for 20 units from plant 1000 to plant 2000 if the plant 2000 has more than 20 units in availability stock and the this stock is above the minimum stock level for the plant.

 

Thank you again for your help.

Regards